One
of the most important responsibilities you may have is
scouting the job
site before designing the wall. The following list is from
the NCMA manual.
If you have a site evaluation to complete, make sure you
address each
of the following items.
- Soil and
fill material should not be frozen
- Foundation
Soil-matches or exceeds soil type and strength
assumed for design
- Retained
Soil-matches or exceeds soil type and properties
assumed for design
- Wall Heights-do
not exceed design heights
- Slopes-no
steeper than design
- Loading-does
not exceed design
Anchor